スプリント バーンダウン (次世代)
This page is for team-managed projects
To check whether your project is or team-managed or company-managed, select More actions (•••) next to the project name in either the header or the sidebar. At the bottom of the menu that opens, you’ll be able to view whether your project is team-managed or company-managed.
If you're in a company-managed project, check out these company-managed project articles instead.
More about the difference between company-managed and team-managed projects.
はじめる前に
In next-gen projects, the Sprint burndown chart can only be used if you have the Reports feature and Sprints feature enabled.
What is the Sprint burndown chart?
A sprint burndown chart shows the amount of work that has been completed in a sprint and the total work remaining. Sprint burndown charts are used to predict your team's likelihood of completing their work in the time available. By tracking the remaining work throughout the sprint, a team can manage its progress, and respond to trends accordingly. For example, if the burndown chart shows that the team may not reach the sprint goal, then the team can take the necessary actions to stay on track.
They're also great for keeping the team aware of any scope creep that occurs.
Learn more about sprint burndown charts at our Agile Coach site.
レポートの読み方
- The vertical axis represents amount of work; either number of issues or story points (if Estimation is enabled). The horizontal axis represents the timeframe of the sprint.
- The grey line shows the ideal progress rate. It trends downwards at a linear rate, because teams should ideally be completing work at a consistent pace.
- The red line shows how much work remains in the sprint. The closer this line is to the grey line, the better.
- The report also has a number of tables that provide more context for the chart. Table data can be sorted by selecting the column header. The tables are:
- Scope changes log: Issues that were added to the sprint, removed from the sprint, or had estimation changes, while the sprint was in progress.
- Incomplete issues: Issues in the sprint that were never completed (ie: never moved to a Done status). This includes issues that were never started.
- Completed issues: Issues that were moved to a Done status while the sprint was in progress.
- Issues completed outside of sprint: This includes issues that were:
- completed and then added to the sprint, either before the sprint started or after the sprint started.
- added to the sprint, but completed before the sprint started.
- Issues removed from sprint: Issues that were removed from the sprint while the sprint was in progress.
その他の注意事項
- 見積機能が有効化されている場合、各課題に対するチームのストーリー ポイント見積りを使用してレポートが表示されます。
- 見積機能が有効化されていない場合、課題の数を使用してレポートが表示されます。つまり、各課題の重みは同等として扱われます。
- レポートは、サブタスクのデータを使用しません (プロジェクトのサブタスクに独自の見積もりがある場合も含む)。ストーリー、バグ、タスクなど、標準レベルの課題タイプのデータのみを使用します。