スプリント バーンダウン (次世代)

お困りですか?

アトラシアン コミュニティをご利用ください。

コミュニティに質問

このヘルプ ページの内容について

以降の情報は、チーム管理対象プロジェクトにのみ適用されます。

どのタイプのプロジェクトの情報を参照すべきかを確認するには、プロジェクトの左側のサイドバーの下部をご覧ください。

  • [チーム管理対象プロジェクトをご利用中です] というアイコンに加えて [フィードバックを送信] や [詳細] メニュー項目が表示される場合は、チーム管理対象プロジェクトを利用しています。

  • そうではない場合は、企業管理対象プロジェクトを利用しています。企業管理対象プロジェクトのドキュメントをご確認ください

はじめる前に

In next-gen projects, the Sprint burndown chart can only be used if you have the Reports feature and Sprints feature enabled.

What is the Sprint burndown chart?

A sprint burndown chart shows the amount of work that has been completed in a sprint and the total work remaining. Sprint burndown charts are used to predict your team's likelihood of completing their work in the time available. By tracking the remaining work throughout the sprint, a team can manage its progress, and respond to trends accordingly. For example, if the burndown chart shows that the team may not reach the sprint goal, then the team can take the necessary actions to stay on track.

They're also great for keeping the team aware of any scope creep that occurs.

Learn more about sprint burndown charts at our Agile Coach site.

レポートの読み方

  • The vertical axis represents amount of work; either number of issues or story points (if Estimation is enabled). The horizontal axis represents the timeframe of the sprint.
  • The grey line shows the ideal progress rate. It trends downwards at a linear rate, because teams should ideally be completing work at a consistent pace.
  • The red line shows how much work remains in the sprint. The closer this line is to the grey line, the better.
  • The report also has a number of tables that provide more context for the chart. Table data can be sorted by selecting the column header. The tables are:
    • Scope changes log: Issues that were added to the sprint, removed from the sprint, or had estimation changes, while the sprint was in progress.
    • Incomplete issues: Issues in the sprint that were never completed (ie: never moved to a Done status). This includes issues that were never started.
    • Completed issues: Issues that were moved to a Done status while the sprint was in progress.
    • Issues completed outside of sprint: This includes issues that were:
      • completed and then added to the sprint, either before the sprint started or after the sprint started.
      • added to the sprint, but completed before the sprint started.
    • Issues removed from sprint: Issues that were removed from the sprint while the sprint was in progress.

その他の注意事項

  • 見積機能が有効化されている場合、各課題に対するチームのストーリー ポイント見積りを使用してレポートが表示されます。
  • 見積機能が有効化されていない場合、課題の数を使用してレポートが表示されます。つまり、各課題の重みは同等として扱われます。 
  • レポートは、サブタスクのデータを使用しません (プロジェクトのサブタスクに独自の見積もりがある場合も含む)。ストーリー、バグ、タスクなど、標準レベルの課題タイプのデータのみを使用します。
最終更新日: 2020 年 1 月 2 日

この内容はお役に立ちましたか?

はい
いいえ
この記事についてのフィードバックを送信する
Powered by Confluence and Scroll Viewport.