よくある質問 (ライブ プラン)
The content in this page pertains to the usage of live plans in Advanced Roadmaps.
プラン
プランは会計年度単位と考慮されますか、それとも個々のプロジェクトとして考慮されますか?
プランはさまざまなレベルで使用できます。プランの使用には一般的なルールはないため、プランの使用方法は通常は作業方法によって異なります。プログラムごとに異なるプランを、次の四半期用に別のプランを、特定のプロジェクト セットに対してプランを作成できます。唯一のルールは、プランは論理的に分離されてリソースの可用性などのデータを共有しないことです。つまり、プロジェクトとチーム間でリソースのバランスを取る必要がある場合は、必ずデータを 1 つのプランに配置します。
What is the functional purpose of an initiative versus a release? How does it relate to Jira projects?
An initiative groups epics and stories into larger chunks of work. Initiatives typically span multiple releases, with intermediate deliveries along the way. Business initiatives will typically encompass substantial scope and investment, and will thus likely represent the level of granularity approved by and reported to top management. Initiatives don't have a direct, binding relation to Jira projects. In many cases, the epics and stories grouped to an initiative live in multiple Jira projects. In other cases, all the issues for an initiative might be in one dedicated Jira project.
動的なプランニングと変更のコミットは区別されますか?
In Advanced Roadmaps, you can play with different scenarios before deciding to commit changes back to Jira. The total number of changes made in your scenario is indicated in an orange bubble at the top of your plan.
You can confirm changes by committing them to Jira, or discard them by reverting them.
範囲
課題 'x' が自分のプランに表示されません
以下を確認してください。
- 対象の課題タイプで fixVersion フィールドが非表示になっていない
- プラン/セットアップ ウィザードで、それを除外するフィルターは設定されていない
- 課題は解決されていないか、インポート ウィザードに表示されません。
- プラン ビューの場合は、[その他] > [オープンおよび完了済みの課題]、または [その他] > [ステータス] > [完了日] の順に移動します。
- 課題は除外されたリリースには含まれません。
- 課題がウィザードで手動で除外されなかった
新しい課題をプランにインポートするにはどうすればよいですか?
Advanced Roadmaps doesn't exactly "import" issues, but lets you set projects/boards/filters as an issue source so that any new issue added to those sources from Jira are automatically added to your plan.
イニシアチブを追加するにはどうすればよいですか?
Initiatives are the high-level priorities that multiple teams or departments work against in an organization or company. Initiatives can span multiple epics, projects, and teams, and the work for initiatives can last months and even years. Using initiatives is essential in Advanced Roadmaps, so you'll need to configure these in your plan hierarchy.
How do I add issues to a sprint in Jira?
You can assign issues to a specific sprint in Advanced Roadmaps, but it requires a small amount of configuration and only works for "board" issue sources.
チーム
I need to manage a mixture of teams that use Scrum and Kanban. Can I still use Advanced Roadmaps?
Yes, Advanced Roadmaps can support a mixture of teams that use Scrum and Kanban. Common to both methodologies is that work on issues must be finished completely before starting work on news ones. If there's sufficient capacity to work on multiple issues, then this will also be reflected accordingly.
Can multiple users be assigned to the same story through Advanced Roadmaps?
Yes, Advanced Roadmaps lets you assign multiple users to the same story. The maximum number of people that can be assigned to a single story is configurable in the settings.
Can Advanced Roadmaps suggest the best teams to assign to initiatives based on the schedule?
If you don't assign a team manually, Advanced Roadmaps will make an automatic assignment, and suggest the teams who can deliver the work the fastest.
Releases
計算中のリリース日内で、リリース スプリント、再発、または安定化への取り組みをどのようにモデル化しますか?
この目標を達成するためのさまざまなオプションがあります。
- 安定化のための作業を表す見積もりを設定した、プレースホルダーのエピックを追加します。フルタイムのスプリントに収まるようにサイズを設定できます。他の作業が完了したあとにのみキャパシティが予約されるようにするため、依存関係や最短の開始日の制約を調整する必要がある場合があります。
- 別のアプローチとして、前のリリースが終了した 2 週後に次のリリースを開始するなど、次のリリースの開始日を変更してリリース間にバッファを残します。
Any plans for sprint capacity planning? I'd like to know where my resource bottlenecks are during a two-week iteration. Jira doesn't do this natively, and as a result, I have to create a capacity plan in Excel.
Advanced Roadmaps should be able to help you with that today. It might be a bit counter-intuitive since you work in sprints, but in order to plan exact capacities on a day to day basis you would have to switch the team to Kanban mode (in the people section, team schedule column). You could use releases to represent sprints instead. This will give you a day-to-day plan within your sprints to see how people are allocated.
レポート
Does Advanced Roadmaps support exporting for reports?
現在、スコープとリリースの CSV エクスポートを利用できます。CSV をダウンロードするには、対象のレポートに移動して右側にあるエクスポート ボタンをクリックします。
スケジュール
このトピックの詳細については「スケジューリングとタイムライン」をご参照ください。