In the new planning experience, we've improved the following functionality:

  • Planning and viewing work: You now have a timeline right next to the issues in your plan. Beside each issue in your plan, line by line, is a corresponding schedule block, which displays when an issue starts and ends in your roadmap. To schedule work, you can manually set target dates, or manually drag and drop the issue blocks in your timeline accordingly.
  • Optimizing your plan: Aside from setting target dates and manually scheduling issues, you can also choose to optimize the work in your plan. By optimizing, Portfolio will use all existing scheduling factors to prepare an optimized schedule for you. You can then choose to accept or discard the proposed changes as needed.

Here is a sample plan in the new experience:


Take note of the following details when using the new experience.

プランの設定

In the new experience, you can currently configure the estimation, issue sources, and permissions being used by a plan. See Configuring plans for more details.

The following settings from the current planning experience are also used as default:

  • 作業時間と作業日
    • 地域: システムの既定
    • 作業日: 8 時間
    • 勤務日: 月曜日から金曜日
  • シナリオ
    • We're still working on supporting multiple scenarios. See Future releases and limitations to know more.
    • As a default, in the case where an existing plan has been converted to the new plan, the current scenario will be used in the new plan. You can also switch to any of the scenarios that may have been set up before the conversion.
  • Commit issue assignee: In the new experience, you now assign issues to assignees, and not team members anymore. With this behavior by default, this option is no longer needed in the new experience.
プラン権限の構成

As a Portfolio administrator, you can choose the users who can make changes in a plan, and the users who can only view a plan.

プラン権限の例

Note that plan permissions are plan-specific, so you'll need to make any necessary changes in each plan. See plan permissions for more details.

作業の表示と管理

In the new experience, plans have three (3) views, which let you focus on specific aspects of your plan.

  • ロードマップ: 管理しているプロジェクト全体で課題を計画し、スケジュールできます。
  • チーム: プラン内のチームを表示、作成、編集、および削除できます。
  • リリース: プラン内のリリースを表示、作成、編集、および削除できます。

See What is a Portfolio plan to know more.

作業の計画

The new planning experience provides an interactive and more intuitive interface for you to view and manage the issues in your plans.

プランのロードマップ ビューには、次のセクションがあります。

  • スコープ セクション: プランのバックログとして機能します。
  • Fields section, which contains pertinent details about the issues in your plan, like status, status breakdown, and estimates.
  • Timeline section, which displays the schedule blocks for each issue in your plan, according to how the issues are scheduled. You can use move blocks to schedule your issues accordingly.

また、プラン内の課題をフィルタリングして、注力する必要のある作業だけを表示できます。プロジェクト、リリース、割り当てのチーム、およびこれらの課題がスケジュールされている時間枠ごとに作業をフィルタリングできます。

See What is a Portfolio plan to know more.

Creating and assigning issues

The new experience provides more obvious and intuitive ways to create issues.

When assigning issues, note that in the new experience, you now assign issues to assignees, and not team members anymore. You can also assign an issue to only one assignee.

See Planning work for more details.

課題のスケジュール

We're simplifying the experience of scheduling issues by using only one type of date — target dates.

You can now interact with the timeline itself to schedule issues:

  • by dragging and dropping the corresponding schedule blocks in the timeline,
  • or by entering target start dates and target end dates for the issues.

You can also set target dates for the issues in Jira itself, if target date fields have already been added in Jira. Any target dates that are set in Jira will also reflect in the corresponding issues and plans in Portfolio for Jira. See Showing Portfolio custom fields in Jira to know how to add target dates to the issue screens in Jira.


You can drag either end of a schedule block, so work for the issue is scheduled for a shorter or longer period of time.

子課題のスケジュール時に、これらの課題の開始日と終了日はその親課題の日付にロールアップされます。実質的には、これは次のことを意味します。

  • 親課題の開始日は、すべてのその子課題の最も早い開始日になります。
  • 終了日はすべての子課題の最も遅い終了日になります。


If you need some ideas on how best to schedule work for your teams, Portfolio for Jira can help you out by optimizing your plan for you. When optimizing your plan, Portfolio for Jira will:

  1. Consider various issue details, including assigned sprints, assigned releases, dependencies, estimates, and target dates.
  2. Give you a preview of how the issues in your plan would be scheduled.
  • The optimized changes will not be automatically saved when these changes display in your plan. You can choose to accept the optimized changes, or return to your plan to make other changes accordingly.
  • For Portfolio to optimize your plan and produce a realistic schedule, you need to estimate the issues in your plan and set up the capacity for your teams.

See Scheduling work and Saving changes in Jira for more details.

課題のランク付け

When you rank an epic with child issues higher, the ranking of its child issues will also be higher. When these changes are committed to Jira, the child issues will also be ranked higher in Jira.

特にチームのバックログまたはアクティブ スプリントで課題のランク付けがすでに行われている場合、こうして子課題のランクが突然上がると、混乱を招くことがあります。

In the new experience, the ranking of child issues is now independent of the ranking of their parent issues. If you rank a parent epic higher, the ranking of its child issues in Jira will stay as is.

進捗を計算する

Progress is calculated by the percentage of estimates completed against the total estimates.

In the new experience, we now display progress more visually — you'll see a status breakdown bar, which displays issues grouped by status category:

  • blue, for issues that are still in the To do status category
  • yellow, for issues in the In progress status category
  • green, for issues in the Done status category

Jira で変更を保存する

  • Any changes you make in your plans will not be saved in Jira, until you're comfortable with the changes made. These include the manual changes you make in your plan, and the optimized changes that you may have accepted.
  • どの変更を Jira に保存するかは、確認して選択できます。詳細については、「Jira で変更を保存する」を参照してください。
チームの管理

チーム ビューでは、以下のことが可能です。

  • Create teams and add members to teams
  • Set the working hours for team members
  • Choose the scheduling method for your teams
  • Assign tasks to teams accordingly

We're still considering how best to manage capacity in the new experience. We're starting with the following details:

  • Currently, only team capacity can be defined. More focus on individual capacity is planned for the future.
  • When optimizing a plan, Portfolio for Jira will consider the total capacity of a team, to complete the work being scheduled.
  • For Portfolio for Jira to do this, you must directly set up the capacity for your teams.

See Managing teams to know more.

リリースを管理する

リリース ビューでは、以下のことが可能です。

  • プロジェクト固有のリリースとプロジェクト横断型リリースを作成し、管理する
  • これらのリリースの進捗を追跡する
  • これらのリリースが、計画どおりのタイミングで完了するかどうかを判断する

We're still considering how best to manage releases in the new experience. At the moment, the dynamic, optimized dates of releases will not be visible.

See Managing releases to know more.

Opting in and out of the new experience

While we've released heaps of features and improvements, we understand that you may need some features that are not available yet. If this is the case, you may need to opt out of the new experience while we're building more functionality. See Future releases and limitations for the current limitations.

We'll announce new features and improvements as we roll them out in future releases. Check out our release notes for updates.


We hope you do opt in again, as we iterate on and release more features over time. See 
Setting up the new experience for more details.