Documentation for GreenHopper 6.1.x. Documentation for other versions of JIRA Agile is available too.
GreenHopper is now called JIRA Agile. Learn more.

You can remove an issue from a planned sprint, or from the sprint that is currently in progress (the active sprint).

(info) 注意:

  • 本ページは スクラムボードにのみ適用されます。

  • You will need to have the 'Edit Issue' permission in the project to which the issue belongs.
  • If you are moving the issue above or below other issues, you will need to have the 'Schedule Issue' permission in the project to which the issue belongs.

Removing an Issue from a Planned Sprint

A planned sprint is a sprint which not yet started. Your planned sprints are visible in  Plan mode, but not in Work mode (since Work mode only shows the active sprint).

To remove an issue from a future sprint,

  1. JIRAにログインします。
  2. 上部ナビゲーションバーで Agile リンクの下矢印をクリックし、表示されるドロップダウンメニューから目的のボードを選択します。

  3. ボードが表示されます。
  4. Click Plan.
  5. Drag the issue out of the planned sprint and into another sprint or into the backlog.

Removing an Issue from an Active Sprint

Sometimes you may need to remove an issue from an active sprint — that is, a sprint which is currently in progress (ie. the sprint which is currently visible in Work mode). Note that removing an issue from an active sprint will be shown as a 'scope change' event on the Burndown Chart for that sprint.

To remove an issue from the active sprint,

  1. JIRAにログインします。
  2. 上部ナビゲーションバーで Agile リンクの下矢印をクリックし、表示されるドロップダウンメニューから目的のボードを選択します。

  3. ボードが表示されます。
  4. Click Work, then click the issue key to display the Issue Detail View at the right of the screen. Select Remove from Sprint from the cog menu (see screenshot below).
    (info) Note that you cannot remove a sub-task from a sprint, as sub-tasks always belong to the same sprint as their parent.

Screenshot: removing an issue from an active sprint (in Work mode)