A burndown chart shows the actual and estimated amount of work to be done in a sprint. The horizontal x-axis in a burndown chart indicates time, and the vertical y-axis indicates cards (issues).

Use a burndown chart to track the total work remaining and to project the likelihood of achieving the sprint goal. By tracking the remaining work throughout the iteration, a team can manage its progress and respond accordingly.

(info) This page only applies to Scrum boards.

To view the burndown chart:

  1. 上部ナビゲーションバーで Agile リンクの下矢印をクリックし、表示されるドロップダウンメニューから目的のボードを選択します。
  2. Click Report, then select Burndown Chart. The burndown chart for your active sprint will be displayed (see screenshot below).
    (tick) To choose a different sprint, click the sprint dropdown.

注意:

  • The burndown chart is board-specific, that is, it will only include issues which match your board's Saved Filter.
  • 縦軸は、設定済みの見積統計を表します 。
  • スプリントの終了時に未完了となっている課題の一覧は、ページの下部に表示されます。
     
スクリーンショット:バーンダウンチャート (クリックで拡大)