If your project administrator has configured statistics (e.g. story points, time tracking) against your versions, you can set statistical markers on your Planning Board to help you see how much work can be assigned to a version.

A typical scenario where you would use a statistical marker is:

  • You have set up story points for your project (a story point is just a custom statistic named "Story Point". See Configuring a Custom Statistic for instructions).
  • You have configured a maximum capacity of Story Point values for your versions.
  • You want to assign issues from your backlog to a version based on issue ranking and your team's velocity (story point capacity per sprint).

To use a statistical marker on your Planning Board,

  1. Jira にログインするか、すでにログインしている場合は、ダッシュボードに移動します。
  2. Click the 'Agile' link's down-arrow in the top navigation bar and select 'Planning Board' from the resulting dropdown menu. The 'Planning Board' will be displayed.
  3. Select your project from the project dropdown at the top left of the Planning Board, if it is not already selected. The 'Planning Board' will refresh with information for your project.
  4. View your issues by version (as described in Using Planning Board Modes to View Issues).
  5. Display the issues for your selected version by clicking the header of the relevant version box in the right column (e.g. click 'Unscheduled' to display the issues in your backlog).
    (info) You may also find it easier to view your issues as a list rather than as cards.
  6. Use a context to sort your issues by the GreenHopper rank field.
  7. Click the icon next to the desired statistic (e.g. 'Story Points', 'Time estimate'), in the version box for the currently displayed version. The page will refresh and display a statistical marker (i.e. grey separator row) against your issues (see 'Statistical Marker Example' screenshot below). The statistical marker will have a number on the right of the separator row (editable by project administrators only) indicating the statistical value that you are grouping your issue by (e.g. 12 story points). The marker will be placed just above the first issue on the project board that will cause this statistical value to be exceeded.
    Screenshot: Statistical Marker

    1 Name of the statistic being used as a marker
    2 Capacity — 'Max' value of statistic
    3 Marker Value — Value currently being used to determine position of marker
    • If the Capacity and the Marker Value are not the same then an arrow appears between the two. Clicking the arrow will reset the Marker Value to the Capacity.
    • If a 'texture' symbol appears in the middle of the bar, then you can drag the bar to schedule all the issues above it.

      Consider the scenario where you want to assign issues from your backlog (unscheduled issues) to a version. You know that your team only has the capacity to do 12 story points worth of work for a version. You can display the statistical marker for 12 story points against your list of unscheduled issues on the Planning Board. The marker will display just above the first issue that will exceed the 12 story point limit. Hence, everything above the line can be dragged and dropped to the desired version without exceeding the team's capacity. See the 'Statistical Marker Example' screenshot below for an example of this scenario.

  8. (project administrators only) To change the value of the statistic being grouped against, edit the value in the textbox on the right of the statistical marker row and press Enter (on your keyboard). You can also set the value to the capacity (i.e. max values specified when configuring the statistic for your Planning Board). The Planning Board will refresh and the statistical marker will be moved accordingly.

Screenshot: Statistical Marker Example