タイムラインで課題のランクを付ける

お困りですか?

アトラシアン コミュニティをご利用ください。

コミュニティに質問

Along with functions like dependencies, ranking issues tells Advanced Roadmaps in which order your work is to be completed. Issues are ranked relative to other issues of the same hierarchy level in your plan. These rankings can’t be surfaced in Jira Software, but they’re essential for using the Auto-scheduler.

Advanced Roadmaps displays an issue’s ranking in the Scope column under # of the highest hierarchy level displayed in your plan. All issues are ranked relative to those with the same hierarchy level, meaning the ranking of an epic won’t impact the ranking of a story.

同じ階層内の課題に対して子課題がどのようにランク付けされているかを確認するには、タイムラインに表示される階層範囲を絞り込みます。

To change the ranking of one issue in Advanced Roadmaps, drag and drop an issue to a new row in the Scope section. Its child issues will move with it to the new row on your plan, but their ranking won’t be changed in Jira SoftwareIf you want to re-rank multiple issues at one time, see Edit issues in bulk from your Advanced Roadmaps timeline.

Any changes you make won’t be reflected in your Jira instance until you save them to Jira.

最終更新日: 2021 年 10 月 6 日

この内容はお役に立ちましたか?

はい
いいえ
この記事についてのフィードバックを送信する
Powered by Confluence and Scroll Viewport.