Resolved Issues are showing up in Advanced Roadmaps Plans even with Exclusion Rules in Jira

お困りですか?

アトラシアン コミュニティをご利用ください。

コミュニティに質問

プラットフォームについて: Server および Data Center のみ。この記事は、Server および Data Center プラットフォームのアトラシアン製品にのみ適用されます。

サーバー*製品のサポートは 2024 年 2 月 15 日に終了しました。サーバー製品を利用している場合は、アトラシアンのサーバー製品のサポート終了のお知らせページにて移行オプションをご確認ください。

*Fisheye および Crucible は除く

 

要約

Resolved Issues are still showing up in the Roadmap Plan even when there's an Exclusion Rule to filter them out.

The Exclusion Rules may be set to consider Issues resolved only in the past 30 days, but Issues resolved longer ago still show up.


環境

All versions of Jira Software 8 and 9 (Data Center or Server).


診断

Confirm if the Issues being shown adhere to these:

  1. They are all in "Done" Status Category (green Status lozenge)
  2. They all have the Resolution field set, and also the Resolution Date
  3. They were resolved before the resolution date threshold configured in the Plan "Exclusion Rules" (default 30 days)
  4. All Issues below in the Hierarchy also adhere to the same 3 rules above

For item #4, you can run this JQL replacing "JIRA-123" by Issues that are resolved and should not be showing up:

key in ("JIRA-123", childIssuesOf("JIRA-123"))

Configure the Filter Results to display these columns:

課題タイプ課題キーステータスソリューション

解決済み

Resolved is the "Resolution Date". Confirm if all Issues that show up in JIRA-123's hierarchy are all in a "Green Status", have the Resolution set (i.e. not "Unresolved") and if the "Resolved" date is beyond the threshold in the Plan Exclusion Rules.


原因

If there's an Issue in the Hierarchy that is not Resolved (or properly Resolved, like missing the Resolution field or date), Roadmap Plans will exhibit the Issues in the Hierarchy on the Plan even if they themselves were resolved long ago.


ソリューション

You may properly Resolve the Issues identified in the Diagnosis step and wait for the Resolution Date threshold to roll-past the cutting date.

To validate the fix, you may:

  • Properly resolve the Issues (have them in a "Green Status"; have the Resolution set and Resolution Date)
  • Update the exclusion rule to 0 Days:

  • Validate the Issues are excluded from the Plan now



最終更新日: 2023 年 12 月 8 日

この内容はお役に立ちましたか?

はい
いいえ
この記事についてのフィードバックを送信する