When linking dependencies of upstream or downstream between stories, 1 day and due date is automatically populated. 

診断

Client is using BigPicture - for ppm, project management for resource management

原因

This is default behavior in BigPicture - for ppm, project management when synchronizing with JIRA.

回避策

Ensure that all settings are configured for the BigPicture Gantt configuration, and Task period configuration is no synchonizing.

  1. Go to ⚙ > System > BigPicture > Gantt configuration
  2. Ensure all fields are completed
  3. Turn off 'Task period configuration'