Managing Portfolio dependencies
アドオンの管理
このページの内容
関連コンテンツ
- 関連コンテンツがありません
You can configure Portfolio for JIRA to use issue links in your JIRA application to define scheduling dependencies.
依存関係を定義する方法
- Ensure that you have issue links between dependent issues in JIRA.
- Go to Portfolio (in header) > Administration > Portfolio Dependencies.
- 必要な課題リンクのタイプを追加します。
- If necessary, click Swap to set the correct dependency orders.
- Portfolio for JIRA's schedule will now consider the issue links as scheduling dependencies.
- [変更を保存] を選択します。
例
If issue A is "blocked by" issue B in your JIRA application, this means you want Portfolio for JIRA to always schedule issue B before issue A.
- Go to Portfolio > Administration > Portfolio Dependencies and add the "blocks" link type.
- If necessary, click Swap to ensure ordering reads "If A blocks B then A is scheduled before B".
- 変更を保存をクリックします。
In your plan, click Recalculate.
注意
In Portfolio for JIRA, the block dependency is set by default.
最終更新日 2018 年 5 月 30 日
関連コンテンツ
- 関連コンテンツがありません
Powered by Confluence and Scroll Viewport.