症状

Occasionally builds never stop running. The build will appear to be running indefinitely thus blocking the agent from taking other builds. In some cases, we have to restart the agent/server to get this agent released. The following stack trace is reported in the logs:

Build <key> had to be cancelled: it was marked as in progress in DB but Bamboo has no record of this build

原因

The cause of this issue may be:

  • The agent dies while processing a build
  • The server still processes a build that was produced by an agent that went offline
  • The agent connectivity was interrupted
  • The agent or server exhausts resources (OOM errors)

ソリューション

Upgrade Bamboo to 5.11.3 or newer versions.