After adding a dependency to an issue, you can easily adjust the dates of the linked issues by dragging either end of the schedule block.

If you reschedule an issue that results to conflicting dates for any of its dependent issues, then the corresponding number badges of the affected dependencies will turn red.

Issue dependencies with aligned dates

Red number badges, indicating conflicting dates for issues with dependencies

Dependency scheduling settings

The occurrence of conflicting dependent issues in your plan is also based on the settings that you configure for dependency scheduling in your plan. The following settings are available:

スケジューリングの挙動説明
SequentialDependent issues cannot be worked on at the same time, whether the issues are manually scheduled or auto-scheduled.
ConcurrentDependent issues can be worked on at the same time, whether the issues are manually scheduled or auto-scheduled.

For example, you have the following in your plan:

  • You have dependent stories TIS-1 and TIS-2, with TIS-1 blocking TIS-2.
  • You have Sprint 1 as the immediate sprint in your plan, and Sprint 2 and Sprint 3 following it.
  • Both issues have the same target start and end dates.
  • Both issues are estimated at 30 story points.
  • 両方の課題が同じチームに割り当てられ、チームのベロシティが 30 ストーリー ポイントとなっています。
  • Both issues are not currently assigned to any sprint.

While the issues have no assigned sprint, the badges will turn red. This is because the dependent issues have the same target dates, which is not a realistic schedule because TIS-1 is blocking TIS-2. Thus, the badges will turn red.

Impact of dependency scheduling settings

上記の詳細を踏まえて、両方の課題が 1 つのスプリント全体を消費すると見積もられているので、課題が同じスプリントにスケジュールされると、数字バッジが赤色に変わります。これは、課題の手動スケジュールにも自動スケジュールにも適用されます。

If the issues had an estimate of 15 story points each, then the following will happen based on the setting chosen:

Sequential
  • The dependent issues will be auto-scheduled into Sprint 1 and Sprint 2. The number badges will not turn red.
  • 課題を同じスプリントに手動で割り当てると、数字バッジが赤色になります。これは、依存課題は別のスプリントにスケジュールする必要があるためです。
Concurrent
  • The dependent issues will be auto-scheduled into the same sprint, Sprint 1. The number badges will not turn red.
  • If you manually assign the issues to Sprint 1, the number badges will still not turn red. This is because dependent issues can be scheduled and worked on in the same sprint.

プランの自動スケジュールを行う際、依存関係の詳細に表示されるリード タイム自動スケジュールされた値になることに注意してください。表示されるリード タイムの値は新しい値で、提案された変更が承認されると更新されます。

Sample lead time of a dependency when a plan is auto-scheduled