Configuring issue dependencies

お困りですか?

アトラシアン コミュニティをご利用ください。

コミュニティに質問

If you've already configured issue links in your Jira instance, you choose to use these issue links when defining scheduling dependencies in your plans.

When adding issue links to your plan, make sure to define the relationship between the issues to suit how your teams work.

Note that any changes you make to issue dependencies will apply to all existing plans.

To define dependencies:

  1. Go to Portfolio (in header) > Administration > Portfolio dependencies.
  2. Add the issue link types that you need.
  3. If necessary, click Swap to set the dependency order that suits your team.
    For example, for the Blocks issue link, the default dependency order is If A blocks B then A is scheduled before B. This means that if Issue A blocks Issue B, Portfolio for Jira will schedule Issue A before Issue B.
    If the reverse dependency order suits your team better, you can swap the order around to: If A blocks B then B is scheduled before A. Portfolio for Jira will then schedule Issue B before Issue A.
  4. [変更を保存] を選択します。

In Portfolio for Jira, the block dependency is set by default.

Last modified on Mar 25, 2020