Using the target schedule report

お困りですか?

アトラシアン コミュニティをご利用ください。

コミュニティに質問

In this report, you can see your scheduled target dates.

  1. Go to Portfolio >Reports > Switch report and select Target schedule.
  2. Now you can see your current target schedule.
  3. Select  to open the schedule settings and select the filters you want to apply. 

    Report setting 説明
    Line Select 'Global' to see all work items on a single timeline. Select 'Projects' to see multiple timelines, one for each project.
    Coloring It shows the colors configured in the stages or in the themes section.
    Zoom Zooming in and out.
    Show empty releases Show or hide empty releases.
    Sprints and stages Use this mode to display the timeline filtered by sprint and stages color. When you click the sprint name, you'll be able to see the sprint capacity availability and usage. Learn more about the capacity view here.
    Show dependencies Show dependency indicators on dependent work items.
  4. You can also switch the report by clicking switch view.

     

 

最終更新日 2017 年 11 月 22 日

この内容はお役に立ちましたか?

はい
いいえ
この記事についてのフィードバックを送信する