This feature allow you to have more control on how things are scheduled. Defines how Portfolio's scheduling algorithm can sequence your issues with dependencies.

  1. Go to  > Scheduling > Scheduling options > Dependency scheduling and select the option you want to apply:

Option 1-Rank dependent work item below required item (Set by default)

Story 1 is blocked by  Story 4

This option will make the schedule move Story 1 below Story 4 during scheduling.

The stories between Story 1 and Story 4 will be ranked above Story 4 and Story 1 during scheduling.

 

Option 2-Rank required work item above dependent item

Story 1 is blocked by Story 4

This option is saying: move Story 4 above Story 1 during scheduling. 

All the stories in between Story 1 and Story4 will be ranked above Sa and Sb during scheduling

Option 3-Off

The schedule ignores dependencies and therefore, takes the standard ranking of those items. The dependencies will be still visible in the schedule.

 

関連トピック

                   Configuring plan settings

                   Scheduling unestimated items based on default estimates

                   Scheduling unestimated items based on target dates

                   Working with default estimate

最終更新日 2017 年 7 月 24 日

この内容はお役に立ちましたか?

はい
いいえ
この記事についてのフィードバックを送信する
Powered by Confluence and Scroll Viewport.