Configuring release dates

お困りですか?

アトラシアン コミュニティをご利用ください。

コミュニティに質問

Portfolio for Jira allows you to configure your release dates in a few easy steps:

  1. Go to your plan via Portfolio (in header) > View Portfolio > click your plan.
  2. Click the  Releases tab to display the releases section below the timeline.
  3. Create a new release or select an existing one.
  4. 編集を選択します。
  5. Configure the dates and close the window.

    Start Date 説明
    As early as possible The release will start as soon as there are available resources.
    Fixed date Release start date is set to the chosen date.
    Relative to previous release date This option allows you to specify the amount of time gap that you want to leave once the previous release is finished and the works on the new one starts.
    リリース日 説明
    Fixed date Release end date is set to the chosen date. In the graphical schedule you'll see a buffer if there is free capacity, or it will be shown as overbooked in red color.
    Dynamic release date The release end date will be dynamically settled. The scheduler automatically fits in as many items as possible into the release based on their priority. The release can never get overbooked.