The sprints reports show all the sprints in your plan on a per-team basis, its assigned issues and time span.

Report setting説明
Empty sprintsShows empty sprints as well as sprints that have issues in them. If it's unticked, the empty sprints won't show up.
課題Tick this option to show sprints' issues be displayed.
課題キーSelect it to display the issue's keys in addition to their titles.

To use the sprints report:

  1. Go to your plan via Portfolio (in header) > View Portfolio > click your plan.
  2. Click the Reports tab to display the reports section for your plan.
  3. Click the switch report menu > Sprints.
  4. If necessary, click  and configure the display settings of the report.