Scheduling unestimated items based on target dates

長期間の作業は通常、高レベルな不確実性を持っています。将来の見積もりを詳細に定義せず、高レベルのロードマップの下書きを作成する場合、将来のリリースでこの機能を使用することで、今後についてより詳細に把握することができます。

 Before you begin, make sure the feature is turned on by going to > Scheduling > Unestimated item scheduling.

  1. Select Base on target dates and click Calculate.

If you turn this feature off, unestimated items won't show up in the timeline. 

Unestimated issues don't actually get scheduled but Portfolio shows them in the schedule based on the manual release and sprint assignments available. The visibility of unestimated items is limited to the information provided and comes with the following restrictions:

  • The length of the unestimated items come either from the release or the sprint duration. If you've set both, the sprint length 

    takes priority over the release duration.

  • The Schedule range filter will filter unestimated items out and you won't be able to see them.
  • Even if you have a fix release assignment, the item won't show up if the release doesn't have a duration or fixed end date.


Properties set on the issue

The issue shows up on schedule
_ リリース チーム Members スプリント
Global grouping チーム Members スプリント



 例

You have an epic with several children and none of them has an estimate. 

  1. Assign them to a release that has a fixed end date.
  2. If you now select Calculate, the issues will be shown in the timeline as unestimated issues having the duration of the release.



    Unestimated issues only show up as unestimated if neither the children nor the issue itself has an actual estimate.


最終更新日: 2018 年 9 月 3 日

この内容はお役に立ちましたか?

はい
いいえ
この記事についてのフィードバックを送信する
Powered by Confluence and Scroll Viewport.