Why the dates are not rolling up to the target end dates in the Advanced Roadmap plan

Platform Notice: Cloud Only - This article only applies to Atlassian products on the cloud platform.

Summary

Dates are not rolling up to the target end dates in the Advanced Roadmap plan

Environment

Jira Cloud

Solution

  • It is to be noted that if the issue is assigned to some sprint in the past, the target end date is picked up from that sprint assigned to the issue rather than the rolled-up sprint values from its child issues.

  • If the issue never had a sprint assigned, you would see that the target end date has taken its value from the latest of the rolled-up sprints.

Updated on February 26, 2025

Still need help?

The Atlassian Community is here for you.