症状

When trying to change the Issue Type Scheme of a particular project with a relatively large amount of issues (10,000+) and a number of inactive users is around 20+, the screen hangs when migrating the Issue Type. As an example, migrating from Sub-tasks to Technical Tasks

診断

The process is taking a very long time and eventually, it hangs. At the same time, the user will also experience session timeout.

原因

As of now, the possible reason behind this matter is that it is caused by the number of inactive users / groups (reporters, assignees, etc.) in the project itself. 

回避策

  1. Make changes to the Permission Scheme by granting the Create Issue and Assignable User permission to the inactive user / group.
  2. After that, proceed with changing the Issue Type Scheme of the project. By now, the process should run smoothly without any problems.
  3. Finally, you should be able to remove the inactive users from the Permission Scheme again.