要約

Release Burndown report is showing resolved issues under the incomplete issues section.

診断

Editing an issue and checking the issue history, we can observe that the issue was already resolved, some of them even were completed in another completed sprint not visible in the report.

原因

It might be caused when the Board column setting is incorrect.

  • Only statuses found in the right-most column of the Columns  configuration are considered as completed.

  • More information on the Column  configuration can be found here:

ソリューション

Map all the statuses that should be considered as Done on the right-most column under JIRA Agile column.