This is the alpha version of Portfolio for Jira 3.0 — your sneak peek at the improved functionality that's just around the corner. As such, do note the following:

  • Some features may not be complete just yet, as we're continuously iterating on these.
  • Because it's an alpha version, the documentation will only be visible to you, our alpha users. You will not find any alpha pages in the usual page sidebar.

We've linked the table of contents below, so you can easily navigate to the alpha pages at any time.

計画を作成し、チームのためにいくつかの問題を追加できたので、次は、チームのためにこれらの問題をスケジュールする最適な方法を考えましょう。

In 2.0 plans, issues are scheduled by what we call a scheduling algorithm. The algorithm considers several issue details, to automatically create a sensible timeline of the work that's relevant to you. With the algorithm, it's easier to spot bottlenecks — this gives you a chance to handle these potential problems even before they happen. As handy as the algorithm can be, you don't really see how it works out your schedule. Ultimately, you're only given the resulting schedule.

With experience and some inside knowledge, let's say that you know that an issue should be scheduled earlier than what has been plotted by the algorithm. In 2.0 plans, you'd need to experiment by changing some issue details, to get the algorithm to schedule the issue your way.

In 3.0 plans, you can now quickly drag and drop the position of an issue in the timeline, to schedule work your way. You’ll no longer have to guess what you should do, to get issue PERF-5 scheduled on 16 August 2018.

チームの作業スケジュールを設定する際は、任意の時点で次のいずれかを実行する必要がある場合があります。

課題のスケジュール

Scheduling issues is as easy as adding the duration for issues directly in your timeline. Alternatively, you can add target dates for the issues, and these dates will display in the timeline section accordingly.

1

Set the duration of work for an issue

  1. タイムライン セクションで、期間を設定する課題のを見つけます。
  2. Hover over the row until the + icon and duration for the issue appears.
  3. Click the row to add in the duration for the issue.
    (info) Note that the default duration for issues would depend on the timeframe in which you're viewing the plan:
    • 3M: 1 週間
    • 1Y: 1 か月
    • Fit: The default duration depends on the date range of the issues in the timeline, which in effect, affects the width of the issues in the timeline. If the width fit is small, then the default duration could perhaps be a week or a month.
    • Custom: The default duration depends on the duration that you set between the start and end dates. If you set a short period of time, then the default duration would be shorter as well.
  4. Above the timeline section, click Update Jira.
    In the dialog that appears, if you're happy with the changes you've made, click Update Jira.
2Set the target dates of an issue
  1. In the scope section, find the issue that you're setting target dates for.
  2. Set the target start date and target end date for the issue. This will create a schedule block for the issue in the timeline section.
  3. Above the timeline section, click Update Jira.
    In the dialog that appears, if you're happy with the changes you've made, click Update Jira.

子課題のスケジュール時に、これらの課題の開始日と終了日はその親課題の日付にロールアップされます。実質的には、これは次のことを意味します。

  • 親課題の開始日は、すべてのその子課題の最も早い開始日になります。
  • 終了日はすべての子課題の最も遅い終了日になります。

Rescheduling issues

To reschedule issues, do one of the following actions accordingly:

  • Drag and drop the schedule block of an issue to its new schedule.
  • Edit the duration of an issue by dragging one of the sides of the schedule block accordingly.
  • Change the target dates of an issue in the fields section.

Organizing issues

You can also move an issue to a higher or lower row in the scope section. This can help you organize issues in both the scope section and timeline section.

For instance, in the sample plan below, you can move TIS-126 from issue row #6 to issue row #3. This way, the top 3 issues in the scope section will all have the same target start date of 30 June 2018.

Moving issues in 3.0 plans

  • Moving issues will impact the issue rank in both Portfolio and Jira.
  • When moving a schedule block of an issue or the row of an issue:

    • Moving an issue that has child issues will move the child issues with the parent issue.
    • Moving an individual child issue of a parent issue will move only that child issue.

Optimizing work for your team

As discussed, in alpha, you can now manually schedule work your way to come up with a realistic schedule for your teams. But this doesn't mean that the scheduling algorithm that we know is out of the picture. You can still get Portfolio for Jira to create a schedule for your teams, by optimizing your plan.

Optimizing a plan

When optimizing a plan, Portfolio for Jira goes through the following scheduling factors, to create a schedule for your team:

  • Sprints assigned to the issues
  • Releases assigned to the issues
  • Any dependencies that the issues may have
  • Target start and target end dates of the issues
  • Estimates provided for the issues
  • Team schedules, e.g. working in either sprint iterations, or in a continuous flow of daily tasks
  • The ranking of work items in the scope table

Sample plan in Portfolio for Jira3.0

To optimize a plan:

  1. Above the timeline section of your plan, click Optimize. This will display a preview of the optimized changes that Portfolio for Jira is suggesting for your plan.

    Optimized changes in 3.0 plans

    Note the following details:

    • In alpha, only the target dates are optimized. We'll be adding more issue details to be optimized in future releases.
    • In the timeline section, the optimized schedule blocks will appear in purple stripes. Similarly, in the fields section, the corresponding target dates will appear in purple stripes.

  2. Review the optimized changes more closely by hovering over each change, to see the current value saved in Portfolio, and the new value that will be saved in both Portfolio and Jira, if the changes are accepted.

    In the example below, the current target end date of the issue is 18 February 2019. If the optimized changes are accepted, the new target end date will become 7 February 2019, which is earlier than the current target date by 11 days.


    Comparing current value and new value in 3.0 plans

  3. 次の操作のいずれかを実行します。
    • To save the optimized changes:
      1. Click Update Jira. The 'Update Jira' dialog will display.
      2. If you're happy with the optimized changes, click Update Jira. The optimized changes will be saved in both the Portfolio plan and your Jira instance.
        Note that if you don't want to update Jira with the optimized changes, click Revert all changes in the 'Update Jira' dialog. This will discard the optimized changes, and will return to the roadmap view of your plan.
    • To discard the optimized changes, click Cancel. The optimized changes will be discarded, and will not be saved in the plan, nor saved in Jira.